To see where Prop AA projects are happening in your neighborhood, please visit our Project News webpage and MyStreetSF, an interactive map that shows all projects currently underway that are funded by, or prioritized for funding by, the SFCTA, as well as those for which the SFCTA provides some level of oversight in our role as Congestion Management Agency for San Francisco.
PROPOSITION AA PROJECT SUMMARY
Project Status |
Number of Projects | Prop AA Funds Allocated | Total Project Cost |
Completed |
17 |
$ 19,379,039 |
$ 39,649,713 |
Underway |
9 |
$ 10,555,515 |
$ 50,072,667 |
Planned |
10 |
$ 16,233,543 |
$ 35,588,898 |
Grand Total |
36 |
$ 45,830,647 |
$ 123,601,353 |
COMPLETED PROJECTS
Project Name | Phase | Sponsor* | Prop AA Funds Allocated | Total Project Cost | Open For Use |
STREET REPAIR AND RECONSTRUCTION |
|||||
9th St Pavement Renovation |
Construction |
Public Works |
$ 2,101,136 |
$ 2,781,543 |
2015 |
28th Ave Pavement Renovation |
Construction |
Public Works |
$ 1,169,843 |
$ 2,369,167 |
2014 |
Design, Construction |
SFMTA |
$ 2,525,621 |
$ 6,955,706 |
2017 |
|
McAllister St Pavement Renovation |
Construction |
Public Works |
$ 1,995,132 |
$ 2,763,663 |
2015 |
Construction |
Public Works |
$ 2,145,024 |
$ 3,230,263 |
2016 |
|
Subtotal |
$ 9,936,756 |
$ 18,100,342 |
|||
PEDESTRIAN SAFETY |
|||||
Construction |
Presidio Trust |
$ 350,000 |
$ 1,015,715 |
2014 |
|
8th and Natoma Mid-Block Crossing Signal |
Design, Construction |
SFMTA |
$ 364,578 |
$ 365,000 |
2016 |
Design |
SFMTA |
$ 337,450 |
$ 1,709,925 |
2018 |
|
Franklin and Divisadero Signal Upgrades |
Design, Construction |
SFMTA |
$ 896,750 |
$ 5,485,080 |
2017 |
Pedestrian Countdown Signals |
Construction |
SFMTA |
$ 1,380,307 |
$ 1,946,298 |
2014 |
McAllister Street Campus Streetscape |
Design, Construction |
UC Hastings |
$ 1,702,035 |
$ 2,485,345 |
2015 |
Construction |
Public Works |
$ 163,358 |
$ 6,955,706 |
2017 |
|
Subtotal |
$ 5,194,478 |
$ 13,007,363 |
|||
TRANSIT RELIABILITY AND MOBILITY IMPROVEMENTS |
|||||
Civic Center BART/Muni Bike Station |
Construction |
BART |
$ 248,000 |
$ 915,000 |
2015 |
Design, Construction |
SFMTA |
$ 933,000 |
$ 991,000 |
2016 |
|
24th St Mission SW BART Plaza and Pedestrian Improvements |
Construction |
BART |
$ 713,831 |
$ 4,216,014 |
2014 |
Hunters View Transit Connection |
Construction |
MOHCD |
$ 1,844,994 |
$ 1,844,994 |
2017 |
Muni Bus Layover Area at BART Daly City Station |
Construction |
BART |
$ 507,980 |
$ 575,000 |
2017 |
Subtotal |
$ 4,247,805 |
$ 8,542,0088 |
|||
TOTAL |
$ 19,379,039 |
$ 39,649,713 |
PROJECTS UNDERWAY
Project Name | Phase | Sponsor* | Prop AA Funds Allocated | Total Project Cost | Open For Use |
STREET REPAIR AND RECONSTRUCTION |
|||||
Design |
Public Works |
$ 650,000 |
$ 8,199,591 |
Anticipated open for use May 2018. |
|
Brannan Street Pavement Renovation |
Construction |
Public Works |
$ 2,540,359 |
$ 4,244,926 |
Anticipated open for use in October 2018. |
Subtotal |
$ 3,190,359 |
$ 12,444,517 |
|||
PEDESTRIAN SAFETY |
|||||
Construction |
Public Works |
$ 1,029,839 |
$ 8,199,591 |
Anticipated open for use May 2018. |
|
Haight Street Resurfacing and Pedestrian Lighting |
Construction |
Public Works |
$ 2,052,000 |
$ 10,766,468 |
Anticipated open for use in March 2020. |
Webster Street Pedestrian Signals |
Design, Construction |
SFMTA |
$ 401,794 |
$ 1,945,000 |
Anticipated open for use in February 2018. |
Gough Street Pedestrian Signals |
Design |
SFMTA |
$ 300,000 |
$ 3,350,000 |
Anticipated open for use in April 2019. |
Bulb-outs at WalkFirst Locations |
Design |
SFMTA |
$ 491,757 |
$ 5,491,757 |
Design anticipated to be complete by March 2018; construction anticipated to begin in summer 2018. |
Subtotal |
$ 4,275,390 |
$ 21,287,225 |
|||
TRANSIT RELIABILITY AND MOBILITY IMPROVEMENTS |
|||||
Elevator Safety and Reliability Upgrades |
Construction |
SFMTA |
$ 287,000 |
$ 2,950,000 |
All locations anticipated open for use in March 2020. |
Construction |
SFMTA |
$ 2,465,316 |
$ 11,600,000 |
Anticipated open for use in March 2019. |
|
Subtotal |
$ 2,752,316 |
$ 14,550,000 |
|||
TOTAL |
$ 10,218,065 |
$ 48,281,742 |
PLANNED PROJECTS
Project Name | Phase | Sponsor* | Prop AA Funds Programmed | Total Project Cost | Anticipated Year of Allocation |
STREET REPAIR AND RECONSTRUCTION |
|||||
Geary Boulevard Pavement Renovation |
Construction |
Public Works |
$ 2,397,129 |
$ 6,044,377 |
2017/18 |
23rd St, Dolores St, York St and Hampshire St Pavement Renovation |
Construction |
Public Works |
$ 2,397,129 |
$ 4,400,000 |
2018/19 |
Mission St Transit and Pavement Improvement |
Construction |
Public Works |
$ 2,397,129 |
$ 6,600,000 |
2020/21 |
Fillmore St Pavement Renovation |
Construction |
Public Works |
$ 2,397,129 |
$ 4,300,000 |
2021/22 |
Subtotal |
$ 9,588,516 |
$ 21,344,377 |
|||
PEDESTRIAN SAFETY |
|||||
Potrero Gateway Loop (Pedestrian Safety Improvements) |
Construction |
Public Works |
$ 300,000 |
$ 2,500,000 |
2017/18 |
Vision Zero Coordinated Pedestrian Safety Improvements (Bulbs & Basements) |
Construction |
Public Works |
$ 700,000 |
$ 2,420,000 |
2017/18 |
Arguello Boulevard Traffic Signal Upgrade |
Construction |
SFMTA |
$ 655,000 |
$ 1,934,000 |
2018/19 |
Bulb-outs at WalkFirst Locations |
Design |
SFMTA |
$ 500,000 |
$ 2,375,757 |
2018/19 |
Western Addition (Pedestrian Lighting) |
Construction |
SFMTA |
$ 986,928 |
$ 1,245,757 |
2018/19 |
Subtotal |
$ 3,141,928 |
$ 10,475,514 |
|||
TRANSIT RELIABILITY AND MOBILITY IMPROVEMENTS |
|||||
Construction |
SFMTA |
$ 3,503,099 |
$ 3,769,007 |
2019/20 |
|
Subtotal |
$ 3,503,099 |
$ 3,769,007 |
|||
TOTAL |
$ 16,233,543 |
$ 35,588,898 |
|||
*Sponsor Abbreviations: BART- San Francisco Bay Area Rapid Transit District; MOHCD- Mayor’s Office of Housing and Community Development; SFMTA- San Francisco Municipal Transportation Agency; UC Hastings- University of California, Hastings College of Law |